Structural Engineering Projects Gallery
Canadian Pacific Railroad Bridge Over Black
River, LaCrosse, WI
Project Engineer: Jeremy May. This project involved monitoring the
existing swing span structure during construction of the new
substructure. The existing structure, a Swing Span Truss built in 1902,
was being replaced with a segmental bascule structure. This structure
is part of Canadian Pacific’s mainline from the Twin Cities to Chicago
and averages approximately 50 trains a day. This structure also swings
open to allow up to approximately 20 boats and barges to pass.
Westbrook received the 2005 State Finalist Award in the Engineering
Excellence Competition for this project.
Project Background
During
construction of the east approach substructures the existing piers
experienced settlement reaching up to 14 inches. The settlement was due
to shallow wooden piling supporting the existing piers, the close
location of the new substructure to the existing piers, and
consolidation of the surrounding loose granular soil due to the
vibratory and hydraulic hammer used to drive the piling.
To complete the substructure portion of the
project, two piers remained to be constructed within 30 feet of the
existing swing span pier. The 14 inches of settlement encountered at
the approach piers would not be acceptable at the swing span pier. The
swing span pier had an allowable settlement of 5 inches controlled by
the elevations of the approach piers and the mechanical components of
the swing span structure required to keep the structure operational.
Due to the high amount of barge and train traffic
it was important to keep the swing span operational during construction
of the two remaining piers. Due to the loose soil conditions the
contractor used jetting to drive the piling. Jetting consists of using
air and water, at high pressures, to drive the piling. The jetting
process would confine vibrations felt at the existing swing span pier
and reduce settlement.
Westbrook Associated Engineers, Inc. Services
The
contractor needed a way to monitor the settlement and provide real time
on-site data to multiple parties involved in the project. Westbrook
provided on-site real time data on Westbrook’s website that would be
used to correlate with settlement readings recorded by SOL Data, a
highly accurate and sensitive survey system based from France.
Westbrook recorded train-crossing times, swing opening and closing times
for barge traffic, along with sheeting and pile driving records.
Westbrook was also responsible for monitoring settlement recorded by the
SOL Data system. The substructure work was completed with minimal
disruption to train and barge traffic. The existing swing span pier
experienced only 1-1/2 inches of settlement.
Additionally, Westbrook designed and developed an
innovative system using
barges and jacking towers to float-out the old bridge and float-in the
new one million pound bridge.
|